3.35 Million Gallon Tank Painting

Click on the photographs below in the slideshow for more information about this project.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

From May through July, 2020 Central Weld County Water District was able to paint one of our 3.35MG tanks.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

Starting in May of 2020, the tank was drained.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

Welding services were able to weld coupons over rusted areas.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

In June of 2020, four steel conduits were welded to the shell of the tank for a mixing system.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

C-supports were welded and an access door was put in.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

Near the first of July, 2020, eight supports columns were cleaned.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

3.35 Million Gallon Tank

3.35 Million Gallon Tank

Near the first of July, 2020, eight supports columns were cleaned.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

A new outlet and drainage pipe connection was facilitated.

3.35 Million Gallon Tank

3.35 Million Gallon Tank

The painting of the tank was finished July 13, 2020.